GOOD Statement by Kaden Arguile,
GOOD National Youth Organiser & City of Cape Town Councillor
18 November 2026
Cape Town’s dams stood at 70.4% yesterday, 13.4 percentage points lower than a year ago, after falling more than a point in a single week.
The city is using 951 million litres a day, 91 million above target and National government has cut allocations from the Western Cape Water Supply System by 7% for domestic and industrial users and 15% for irrigation, warning of a strong to extreme El Niño. Level 1 restrictions start on 1 December.
This is not Day Zero this summer. But after two below-average rainfall years, another dry winter in 2027 would find Cape Town with almost no new water that does not depend on rain.
That is exactly the risk the City promised to remove.
The promise:
The City’s 2019 Water Strategy committed to more than 300 million litres a day of new water within ten years, with protection against a 1-in-200-year drought. Its timetable promised schemes worth 347 million litres a day by the end of 2026, 265 million of it from groundwater, reuse, desalination and the Berg River.
The delivery:
In 2025 the groundwater schemes at Steenbras and Atlantis produced about 3 million litres a day, by the City’s own figures. Only Steenbras is new. The Cape Flats aquifer has supplied nothing for use. Reuse, desalination and the Berg River–Voëlvlei scheme have not delivered a single litre.
The Faure reuse scheme, due in 2024, is now expected in 2031. The full programme has slipped from 2030 to 2036.
Lowering the bar:
Rather than catch up, the City lowered the bar. Its 2026 Water Outlook, published on 19 August, the day before the last council meeting of the term, accepts that until around 2030 Cape Town will have only 1-in-50-year protection “with no allowance for climate change”.
It now plans for a middle-of-the-road climate scenario because “planning for a high climate change scenario would not be financially affordable”.
Even restrictions came late. The strategy says Level 1 should apply when dams are below 80% on 1 November. They were at about 73%, and the City acted only after national government cut allocations.
The wrong choices:
These are not just delays, they are a result of choices.
The City’s long-term bet is desalination – a 70 million-litre-a-day plant at Paarden Eiland, put at about R5 billion, and planning for a second plant of up to 360 million litres a day.
GOOD has never supported desalination as Cape Town’s answer, because it is expensive to run. Seawater desalination typically uses 3.5 to 4.5 kWh of electricity per kilolitre, roughly double water reuse, much of it bought from Eskom.
The City’s own 2019 strategy priced desalination’s running costs at R9 a kilolitre, against R5 for reuse, R2 to R8 for groundwater and R3 for demand management.
Even on its own terms the bet has not delivered – the plant has slipped from 2026 to 2036, and Transnet’s port plans have put its site in doubt.
Meanwhile the cheaper options were starved. Faure waited until December 2025 for a procurement decision.
Demand grew about 5% last year, more than three times the rate the City’s conservation strategy plans for, and that strategy is R6.7 billion short of funding.
Who pays:
The Outlook warns that the cost of water “will increase substantially over the next few years”. The 2019 strategy said the price of water would ultimately “settle at the cost of providing additional desalinated water”, then estimated at R15 to R25 a kilolitre.
Trade press, reporting the City’s own modelling, put the Paarden Eiland plant alone at real tariff increases of 6.57% and 6.63% in its first two planned years of operation. This year’s tariffs already rise 9.3% and 14.12% on the upper consumption steps.
Working families and the poorest must not pay Eskom-driven running costs for decades while cheaper water is left undeveloped.
GOOD demands:
GOOD calls on the City of Cape Town to publish a scheme-by-scheme delivery schedule, with metered output, updated every quarter; bring the downgrade of the 1-in-200 standard to a full Council debate and vote, with a funded plan to restore it; put reuse, groundwater and loss reduction first: fast-track Faure and the aquifer schemes, and cut leaks and non-revenue water before winter 2027; publish desalination’s full lifetime cost, including electricity and tariff impact, before committing another rand; and shield poor households from drought-driven tariff hikes.
Drought was the reason for the 2019 plan, not an excuse for failing to deliver it.
Had the City built its own plan with the urgency it promised after Day Zero, Cape Town would today have new water that does not depend on rain.
Instead, schemes have been delayed for years, and the City’s long-term bet is on the most expensive option.
That leaves us once again relying on the weather. If the 2027 winter is dry, the risk of a real Day Zero returns, and it will be a crisis of the City’s own making.
Media Enquiries: media@forgood.org.za